Touchwood Homes

Current build

November 2019

We’re now working in Winchester building a 175 m2 two storey passivhaus home which includes a garage / office building also on site.

The timber frame for the home erection was completed in just two weeks, so we have been able to move on to the next phase of creating our super-airtight cladding layer which we can expect to produce levels of around 0.3 ach, which is better than the standard required for passivhaus!

Once we’ve completed this, we will be starting work on the garage / office structure which is to include integrated oak posts and beams, as our client wanted to create a warm and rustic feel to the building. Our non panalised build system allows us so much flexibility over the design of buildings that including such integrated features causes no difficulties at all.